                                              Rates, Norms & Durations

                                              681
                                              What is needed to come up with a production rate?

                                              A duration of time, the manhours involved, and an amount of work produced?

                                              This section is here to document this.  What information do you have that you can share?

                                              Comments

                                              MEP Productivity

                                              Hello sir, If you have any data related to MEP activities productivity rates for gulf countries, request you to kindly share on nimish93@gmail.com Regards, Nimish R Swami

                                              Metsec output rates

                                              Hi, Has anyone got any information of Metsec output rates please

                                              MEP PRODUCTIVITY rate reference

                                              MEP productivity rate norms::

                                              Does anyone know where to get the Productivity rate of MEP work that trust worthy and can be used as reference to support the duration calculation. 

                                              greatly appreciate,

                                              pisan_osk@hotmail.com

                                              Manual Rates

                                              Hi,

                                              It seems that the most of the rates here are equipment rates. do you have any rates for manpowered activities (e.g. manual excavation)

                                              Productivity rates for "Civil Infra. and Oil & Gas Projcts

                                              Dear Friends,

                                              I need the productivity rates for "Civil Infrastructure and Oil & Gas Projcts" of Middle East Countries. Any one can help ? Please send the excel/word sheet to my e-mail id:

                                              ramanannagamani@gmail.com

                                              Thanks.

                                              Ramanan

                                              Drainage outputs

                                              looking at the drainage outputs on here they don't seem to be that reliable? does anybody have an excel spreadsheet they would be able to send with some general drainage outputs?

                                              ManPower Productivity Norms for MEP

                                              hi,

                                              Anyone having Manpower productivy norms excel file for MEP(Gulf), it will be very helful to me.

                                               

                                              e-mail: hariveerendra@gmail.com

                                              Drainage outputs

                                              I am struggling to see any logic behind the productions per hour on the drainage?

                                              33m per hour for 150mm drainage in runs exceeding 30m or greater is impossible - unless installed via trenchless methods!

                                              I calculate my drainage productions to include dig, bed and surround, pipe laying and backfilling compacting in accordance with the specification and would never price on more than 30 - 35m per DAY for a 150mm UPVC pipe at a depth not exceeding 1m.

                                              What do the productions on here realte to and what do they include?

                                              Drainage outputs

                                              I am struggling to see any logic behind the productions per hour on the drainage?

                                              33m per hour for 150mm drainage in runs exceeding 30m or greater is impossible - unless installed via trenchless methods!

                                              I calculate my drainage productions to include dig, bed and surround, pipe laying and backfilling compacting in accordance with the specification and would never price on more than 30 - 35m per DAY for a 150mm UPVC pipe at a depth not exceeding 1m.

                                              What do the productions on here realte to and what do they include?

                                              Contact JEPM LLC at 409-457-7725

                                              What geographical location is labor being executed? (remote/local port)

                                              What is the weather conditions?

                                              What type of industry?

                                              Other particulars or need; Are there readily available resource (MP & DFL Equip/Consumables) ?

                                              Please feel free to contact me at your convenience. 

                                              Once we come into mutual agreement, I will produce the needed excel loaded unit rates for your project/s need/s.  Based on execution industry actuals.

                                              Best regard,

                                              JEPM LLC

                                              Project Controls Engineer SME

                                              Jacob Armstrong

                                              409-457-7725

                                              Project Controls SME

                                              Are you in need still?

                                              Jaocb Armstrong JEPM LLC  409-457-7725

                                               

                                              Ya, I am waiting for

                                              Ya, I am waiting for comments. If you can give some feedback/ comments, it will greatly be useful.

                                              Thanks/Regards,

                                              Santhosh

                                              Impact of crew size and composition on productivity

                                              Ya, I am waiting for comments. If you can give some feedback/ comments, it will greatly be useful.

                                              Thanks/Regards,

                                              Santhosh

                                              Project Controls SME

                                              Are you in need still?

                                              Jaocb Armstrong JEPM LLC  409-457-7725

                                              Impact of crew design (crew size and composition)on productivity

                                              Hi all,

                                              Can you comment on impact of crew design, i.e crew size and composition on productivity?

                                              Thanks,

                                              Santhosh

                                              Construction labour rates

                                              Dear all experts;

                                              This data is very useful for me and thank you all. But i need construction labour rates as an excel file. If somebody has it and sen me i will very be thankful. Also can you please give a book advise for this issue.

                                              Thank you all.

                                              efe.gurkan@hotmail.com

                                              productivity rates

                                              Dear all experts,

                                               

                                              I need the productivity rates for Oil & Gas Project - Construction Trade like Sand Blaster, Fireproofer, Spray Painter, Scaffolder, Sheet Metal Fitter, Insulators and Welder.

                                              I will be very thankful if excel file or PDF file of all production rates can be shared on my email address: sukh_shrestha@hotmail.com

                                              Thank You

                                              Productivity

                                              Can i get the production rate dia Inch for CHW pipes for example 20" pipe one joint require 3 hours .. Etc or if there is a formula followed to calculate the same knowing that its all sch STND

                                              Crew structure

                                              Thank you deeply, for the great effort you've been doing.

                                              I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.

                                               

                                              Best Regards,

                                              Crew structure

                                              Thank you deeply, for the great effort you've been doing.

                                              I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.

                                               

                                              Best Regards,

                                              Crew structure

                                              Thank you deeply, for the great effort you've been doing.

                                              I just would like to pay your attention that the productivity rates are in a big need to the crew structure producing these rates.

                                               

                                              Best Regards,

                                              Pluming Productivity rates

                                              Dear all experts,

                                               

                                              I need the productivity rates for first and second fixs for MEP work (HVAc, Firefighting and Plumbing).

                                               

                                              Thank you

                                              Pluming Productivity rates

                                              Dear all experts,

                                               

                                              I need the productivity rates for first and second fixs for MEP work (HVAc, Firefighting and Plumbing).

                                               

                                              Thank you

                                              Excel or PDF format of rates

                                              Good Morning,

                                               

                                              The information avaialble here is very useful for me, thanks a lot.

                                              I will be very thankful if excel file or PDF file of all prodcution rates can be shared on my email address: lnt.vikas@gmail.com

                                              Thanks,

                                              Vikas Budhiraja, PMP

                                              Productivity for Platform fabrication & installation

                                               

                                               

                                              Can anyone help me with the units used to measure progress of platfrom fabrication & welding?

                                               

                                              Is it ok to USE ... Kg of steel fabricated or welded?

                                              Productivity for Platform fabrication & installation

                                               

                                               

                                              Can anyone help me with the units used to measure progress of platfrom fabrication & welding?

                                               

                                              Is it ok to USE ... Kg of steel fabricated or welded?

                                              Partitions

                                              Hi Guys,

                                               

                                              Just like to know if we have productivity rate for glazing partitions..... also there is no productivity rate for plasterboard installation on the partitioning rates.

                                               

                                              Thanks!

                                               

                                              Ruel

                                              MEP Productivity Norms

                                               

                                              S.N0

                                              Activity

                                              Productivity norms

                                              Qty

                                              Units

                                              DUCTING:

                                              1

                                              Duct

                                              1.2 – 1.5

                                              Sqm/man/day

                                              2

                                              Insulation

                                              3

                                              Sqm/man/day

                                              3

                                              1 No - VAV

                                              3

                                              Sqm/man/day

                                              4

                                              1 No - ECV

                                              2

                                              Sqm/ man/day

                                              5

                                              1 No – Joint Insulation

                                              0.4

                                              Sqm/man/day

                                              6

                                              1 No - Flexible Duct

                                              1

                                              Sqm/man/day

                                              7

                                              1 No - Plenum

                                              1

                                              Sqm/man/day

                                              8

                                              1 No - MSFD

                                              2

                                              Sqm/man/day

                                              9

                                              1 No - VCD

                                              1

                                              Sqm/man/day

                                              10

                                              Pressure Test per 25 Sqm ducting

                                              4.5

                                              Sqm/man/ day

                                              11

                                              Multipurpose Supports – 4 No

                                              1.5

                                              Sqm/man/day

                                              12

                                              Grills & Diffusers

                                              6

                                              No’s / Man/ day

                                              13

                                              Linear Slot Diffuser

                                              6

                                              Rm / Man / day

                                               

                                              Kindly note that here ducting  is inclusive Support fixing + Cleat fixing + Sealant application

                                              CHW PIPE:

                                              1

                                              1" – 2" dia

                                              7.5

                                              Rm/man/day

                                              2

                                              2" - 3"dia

                                              5

                                              Rm/man/day

                                              3

                                              4"dia

                                              2.5

                                              Rm/man/day

                                              4

                                              6"dia

                                              1.5

                                              Rm/man/day

                                              5

                                              8"dia

                                              1.2

                                              Rm/man/day

                                              6

                                              10"dia

                                              1

                                              Rm/man/day

                                              7

                                              CHW Pipe Insulation

                                              15

                                              Rm/man/day

                                              8

                                              Pressure Test for 100 Rm

                                              3

                                              man/day

                                              9

                                              Valve Package

                                              1.5

                                              Man / day / unit

                                               

                                              Kindly note that here Chilled water piping is inclusive of Support fixing

                                              S.N0

                                              Activity

                                              Productivity norms

                                              Qty

                                              Units

                                              ELECTRICAL/ELV

                                              1

                                              Conduit

                                              16

                                              Rm/man/day

                                              2

                                              Wiring

                                              30-40

                                              Rm/man/day

                                              3

                                              Cable tray

                                              5-6

                                              Rm/man/day

                                              4

                                              Trunking

                                              8-10

                                              sq.m/man/day

                                              5

                                              DB Installation

                                              1

                                              Nos/man/day

                                              6

                                              DB Termination

                                              1

                                              Nos/man/day

                                              7

                                              Final Fix Accessories

                                              8

                                              Nos/man/day

                                              8

                                              Light points

                                              8

                                              Nos/man/day

                                              PLUMBING

                                              1

                                              Water supply pipe installation

                                              5

                                              Rm/man/day

                                              2

                                              Drain pipe installation

                                              3

                                              Rm/man/day

                                              Kindly note that Piping Installation is inclusive of Support fixing

                                              Middle East MEP Worker Production rate

                                              Hi all,

                                               

                                              I am also facing problem in sourcing MEP labout production rate for Middle East Region. Anyone can help?

                                               

                                              regards,

                                               

                                              Kevin

                                              Request for clarification....

                                              Hi Frendz ...

                                              I like this section this is helping me in may ways ..but i am facing problem when it comes to productivity rates given without resources, as what resource  should i consider if i want to use these rates please help .......

                                               

                                               

                                              regards,

                                              Khan

                                              Market Place

                                              For 25+ years, APMX has been providing competency based project management training to Fortune 500 companies around the world, applying the principles of project based learning, designed to produce measurable results, generating a favorable “return on training investment”.
                                              See how the TIME - LOCATION - VIEW brings clearness to your work programmes
                                              Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher and PMI accredited REP. Teach yourself using on-line or book based learning or run your own in-house or public PMI accredited courses.

                                                                                          culture

                                                                                          entertainment

                                                                                          news

                                                                                          news

                                                                                          game

                                                                                          Finance

                                                                                          image

                                                                                          Real estate

                                                                                          fashion