Calendar Days do not match Calendar Hours?
Hi,
I have a calendar running 10 hours per day, 5 days per week. It is assigned as the Activity default calendar. When I create a new activity with a duration of 3 days and then change my User Preference to show Duration in Hours, the hours are only 24 but I expected them to be 30.
Why is this happenning? 3 days on a 10 hour per day calendar should be 30 hours but it appears to be referencing an 8 hour day.
You help would be greatly appreciated.
Rod
Brilliant, Yes, it was the Timeperiods.
Thanks.
Rod
you have not set the hours correctly or have not set the correct default calendar
Replies