win|比分

                                              Forum Sponsor:

                                              Portfolio Planner is software which improves portfolio, project and resource management.

                                              Viewer for .xer, xml and xls schedule files Schedule Reader?Free Trial

                                              Tips on using this forum..

                                              (1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

                                              (2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

                                              Showing productivity changes with different Resource Calendars

                                              5 replies [Last post]
                                              Dejan Kezic
                                              User offline. Last seen 2 weeks 3 days ago. Offline
                                              Joined: 21 Mar 2018
                                              Posts: 4
                                              Groups: None

                                              Hi everyone, I am kindly asking for help about following problem.

                                              I need to show lower productivity per several resources in my schedule in winter period. Those resources are commodities.

                                              Other resources (manpower and equipment) as well as activities should be intacted.

                                              So my idea was that I will keep on using original project calendar (7 days x 10 hours) for activities and mapower/equipment resources, and modified calendar (summer months 7 days x 10 hours and winter months 6 days x 6 hours)  for a.m. commodity resources.

                                              Unfortunately it did not show any difference from original schedule and all resources were distributed lineary.

                                              Is there some solution how to get this result?

                                              Thank you!

                                              PS

                                              I should mention that I have changed to different clandar for all activities and it did show changes (higer resources in summer and lower resources in winter), but it does not help me because I don't want to show changes for manpower and equipment (only for commodities).

                                              Also, I know that creating more detailed schedule with activities dedicated to volume of work for winter months will solve problem, but I don't have time and need fast solution.

                                              Replies

                                              Rafael Davila
                                              User offline. Last seen 12 hours 24 min ago. Offline
                                              Joined: 1 Mar 2004
                                              Posts: 4864

                                              Please click the following link to download presentation pdf.

                                              Link to Quantities_Workloads_and_Production_Rates.pdf/file

                                              Best Regard,

                                              Rafael Davila

                                              Rafael Davila
                                              User offline. Last seen 12 hours 24 min ago. Offline
                                              Joined: 1 Mar 2004
                                              Posts: 4864

                                              Dejan:

                                              How do you show productivities in P6 in a transparent way? Where do you enter such values? As far as I recal there is no such functionality in P6?

                                              What do you mean by activities dedicated to volume of work for winter?

                                              Activity might be delayed from winter to summer. And what when a portion falls in winter and another portion fall in summer, this make too many possibilities. Using separate activities may not be a good idea.

                                              Best Regards

                                              Rafael

                                              Raymund de Laza
                                              User offline. Last seen 2 weeks 1 day ago. Offline
                                              Joined: 23 Nov 2009
                                              Posts: 744

                                              Use the REsource Detail: Effectivity and Max Unit per Time

                                              Set the Reduced Max Qty (Max Unit per Time) within the Effective dates.

                                              Rafael Davila
                                              User offline. Last seen 12 hours 24 min ago. Offline
                                              Joined: 1 Mar 2004
                                              Posts: 4864

                                              Zoltan Palffy
                                              User offline. Last seen 22 hours 17 min ago. Offline
                                              Joined: 13 Jul 2009
                                              Posts: 2688
                                              Groups: None

                                              put the resources on a different calendar 

                                                                                          Blog

                                                                                          Technology

                                                                                          video

                                                                                          news

                                                                                          search for

                                                                                          fashion

                                                                                          Real estate

                                                                                          Information

                                                                                          education