P6 Filter
I'm hoping someone can help me. I need to filter my P6 schedule for a 2 week look ahead HOWEVER the PM is looking to also see all milestones - not just the ones within that 2 week period.
Can anyone help?
Thanks!!
Heather,
Use the top row of a filter to change the statement from "all" to "any" and then you can have three rows like this
Row 1) Finish is less than DD+2w (if you want two weeks from the data date, CD+2w if you want from the current date)
OR
Row 2) Activity Type = Start Milestone
OR
Row 3) Activity Type = Finish Milestone