                                              Purpose of Retired activities in Schedule

                                              3 replies [Last post]
                                              Nathan Siva
                                              User offline. Last seen 6 days 23 hours ago. Offline
                                              Joined: 28 Apr 2014
                                              Posts: 25
                                              Groups: None

                                              Hi Expats,

                                              In one of my UK clients schedule, they advised  to retire completed activites and non performing activites in the schedule. and my collegues recommended to change the duration of non performed activities duration to 1D in the schedule to avoid those activities in critical path.

                                              Can you please explain the purpose of retiring the activities in the schedule?

                                              Replies

                                              Zoltan Palffy
                                              User offline. Last seen 22 hours 21 min ago. Offline
                                              Joined: 13 Jul 2009
                                              Posts: 2688
                                              Groups: None

                                              Glad I could help 

                                              Nathan Siva
                                              User offline. Last seen 6 days 23 hours ago. Offline
                                              Joined: 28 Apr 2014
                                              Posts: 25
                                              Groups: None

                                              Thanks for the detailed explanation Zoltan. it  makes sense.

                                              Zoltan Palffy
                                              User offline. Last seen 22 hours 21 min ago. Offline
                                              Joined: 13 Jul 2009
                                              Posts: 2688
                                              Groups: None

                                              an actviity can be in one of 4 categories

                                              not started

                                              in progress 

                                              completed

                                              modified in progress using suspend and resume

                                              whne you say retire completed I do not know what you mean ? I also do not know what a non performed actviities are

                                              if you mean the activities are no longer in the scope then I would should show the same actual start and finish date equal to the date that you were told that this activity is not longer in the scope. 

                                              PUtting 1 day duration WILL make them critical making them complted will not

                                              I would also assign an activity code theses and make a comment in the notes tab. This way you can filter and gropu these if need be. 