Converting .pp (Asta) files to .xer (Oracle Primavera) and importing to P6 - tips
HI
Can anyone provide a list of tips when saving a .pp file as an .xer file and importing to P6. I always get error message in Asta, and when i import to P6, it crashes and forces me to Exit with an error code.
I found an independent list (see below) but wanted to see if anyone knew of more? Our contractor is currently working in Asta and will be migrating to P6 but I need to run a quick analysis of the integrity of the schedule as it stands and want to be sure I'm importing everything I need.
Thanks
Of course (support.elecosoft.com) but more importantly, you can also just give us a call directly and ask!
doesnt Asta have a knowledge base like Oracle does where you can look up the error code to find out what is causing the problem ?
Hi Mike,
What verison of Powerproject are you on? We changed lots of the import/export functions in v15 onwards. Latest helpfile is here: https://help.elecosoft.com/powerproject/english/15.0.02/Content/HTML_Topics/Conceptual/Starting_work/Primavera/Xfer_Primavera.htm
Thanks,
Ben @ Powerproject
Dang - I was hoping for an answer on this question - I am trying to do this today, provide an Asta .pp file that can be uploaded into P6.