                                              Hi experts

                                              I'm writing macro for Asta and hit the wall when I want to assign income value in task.

                                              Below code finds Income Cost Centre assigned, but can't find a way to set value.

                                              Dim t As TaskBase

                                              Dim bcv As BarChartView
                                              Dim ca As CostAllocation

                                               Set bcv = ap.CurrentView
                                               AllTasks = bcv.AllTaskBaseIds
                                                For Each act In AllTasks    
                                                   For i = 1 To t.Allocations.Count
                                                           Set ca = t.Allocations(i)
                                                       'here I need to set income value on this task 
                                                    Next i
                                               Next act


                                              Thank you in advance for any hints!

                                              Replies

                                              Dariusz C
                                              User offline. Last seen 12 weeks 1 day ago. Offline
                                              Joined: 10 Dec 2018
                                              Posts: 7
                                              Groups: None

                                              It wasn't work with ca.Value.
                                              I found that work like below:

                                              The missing code is:

                                              ca.GivenValue = 100 ' or whatever you need

                                              Topic closed :)