win|比分

                                              Tips on using this forum..

                                              (1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

                                              (2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

                                              As built programme

                                              3 replies [Last post]
                                              Chris Wilson
                                              User offline. Last seen 21 weeks 6 days ago. Offline
                                              Joined: 21 Oct 2016
                                              Posts: 17
                                              Groups: None

                                              Hi,

                                              I have a programme where I have been recording progress on a weekly basis but I have not been using it as a live programme i.e one that you reschedule on a weekly basis. I am now trying to crate an as built programme from it.

                                              I know that If I do a reschedule at the last progress period only those activities not complete will shift and complete tasks dont shift from the baseline however I am wanting to show the progress throughout the project.

                                              Does anyone know how to do tihs?

                                              I was thinking I would have to go back to the first progress period and reschedule to that then the 2nd , 3rd 4th etc so activities shfted to period in wihch they were complete but not sure but this seems like a lot of work and not sure how to set reschedule options to only account for the progress at that week in the reschedule.

                                              Any help appreciated.

                                              Regards

                                              Chris

                                              Replies

                                              Stephen Devaux
                                              User offline. Last seen 10 weeks 23 hours ago. Offline
                                              Joined: 23 Mar 2005
                                              Posts: 644

                                              Hi, Mike. Since Asta Powerproject, unlike Primavera, has the ability to compute critical path drag, can I suggest two more columns?

                                              1. As Planned drag.

                                              2. As Built drag.

                                              I also think that tracking changes in drag for each activity (especially when the CP changes causing different activities to have drag) with each new version of the schedule during execution would be VERY valuable from a forensic viewpoint -- but admittedly, that gets a bit more complicated.

                                              Fraternally in project management,

                                              Steve the Bajan

                                              Chris Wilson
                                              User offline. Last seen 21 weeks 6 days ago. Offline
                                              Joined: 21 Oct 2016
                                              Posts: 17
                                              Groups: None

                                              Thanks Mike will give that a try

                                              Mike Testro
                                              User offline. Last seen 2 weeks 4 days ago. Offline
                                              Joined: 14 Dec 2005
                                              Posts: 4403

                                              Hi Chris

                                              Save the file inot a new one.

                                              Transfer all of your weekly progress reports onto a spreadsheet.

                                              Add 2 new columns Start AB plus End AB and transfer the 1st record above 0 and the last record at 100.

                                              You can get accurate dates by interpolating % complete on the days of the month.

                                              Set up your As planned bars as a baseline and then copy/paste your spreadsheet dates into the Start and Finish columns.

                                              You now have an As Planned v As Built comparison programme.

                                              Best regards Mike Testro.

                                               

                                               

                                               

                                               

                                               

                                               

                                               

                                               

                                               

                                               

                                               

                                               

                                               

                                               

                                               

                                               

                                                                                          Go abroad

                                                                                          constellation

                                                                                          Celebrity

                                                                                          explore

                                                                                          culture

                                                                                          Information

                                                                                          fashion

                                                                                          Application Essentials

                                                                                          mailbox