                                              BI Export - working days and elapsed duration

                                              4 replies [Last post]
                                              Dariusz C
                                              User offline. Last seen 12 weeks 2 days ago. Offline
                                              Joined: 10 Dec 2018
                                              Posts: 7
                                              Groups: None

                                              Hi

                                              In my model I extract tasks data according to line below from model file:

                                              <Column name="DurationDays" datatype="Duration" group="Date" formula="Duration / '1d'"/>

                                               

                                              The problem is that some tasks have duration in working days and some of them in elapsed days, please look at attached screenshot for more details.
                                              Working days are not a problem at all. Problem is with elapsed duration

                                              7136
                                              working_vs_elapsed.png

                                              What should I do to get durations in format I have in Powerproject into the same table?

                                               

                                              Thank you in advance for any hint!

                                              Replies

                                              Dariusz C
                                              User offline. Last seen 12 weeks 2 days ago. Offline
                                              Joined: 10 Dec 2018
                                              Posts: 7
                                              Groups: None

                                              Hi Ben

                                               

                                              Thanks for that. This is exactly what I did:

                                               

                                              <Column name="DurationDays" datatype="Duration" group="Date" formula="If(IsElapsedTime(duration) = TRUE, Duration / '1ed', Duration / '1d')"/>

                                              Ben Taunt
                                              User offline. Last seen 6 days 11 hours ago. Offline
                                              Joined: 16 Jan 2012
                                              Posts: 102
                                              Groups: None

                                               

                                              Hi Dariusz,

                                               

                                              There are several potential solutions to this.  The simplest is to add a column that tells you if a task is a Working or Elapsed:

                                               

                                              <Column name="ElapsedStatus" datatype="Boolean" group="Date" formula="IsElapsedTime(duration)" />  

                                               

                                              Cheers,

                                               

                                              Ben @ Powerproject 

                                              Dariusz C
                                              User offline. Last seen 12 weeks 2 days ago. Offline
                                              Joined: 10 Dec 2018
                                              Posts: 7
                                              Groups: None

                                              Hi Mike

                                              Thanks for reply and warm welcome ;)

                                              It's not about Asta Powerproject itself but BI Controller.

                                              These elapsed durations you could see in screenshot are OK, my entire plan contains days and elapsed days.

                                              The problem is coming when I want to export Powerproject data to external datasource.

                                               

                                              For example I've got 2 tasks:

                                              Task 1   , 2d duration

                                              Task 2, 2ed duration

                                              Model files has formula for duration and it "force" to write durations in days:

                                              formula="Duration / '1d'"

                                              But for Task 2 it will return incorrect value becasue of elapsed units...

                                               

                                              With formula:

                                              formula="Duration / '1ed'"

                                              it will return correct values for durations expressed in elapsed days (Task 2), but not for working days (Task 1).

                                              Still with me? :)

                                              I can't find any way to export correct durations via BI Controller regardless of duration units used for tasks.

                                               

                                               

                                              Mike Testro
                                              User offline. Last seen 2 weeks 4 days ago. Offline
                                              Joined: 14 Dec 2005
                                              Posts: 4403

                                              Hi Dariusz - welcome to planning planet.

                                              Right click the duration table - select Format Cells - Left click Duration - select your format "Day".

                                              Best regards

                                              Mike T.