                                              (1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

                                              (2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

                                              Week numbers in the date zone

                                              2 replies [Last post]
                                              Alex Hough
                                              User offline. Last seen 27 weeks 6 days ago. Offline
                                              Joined: 10 Apr 2017
                                              Posts: 7
                                              Groups: None

                                              Hi all

                                              I have a 30 week programme that has a 2 week shutdown over Christmas. The current week numbers in the date zone show it coming out as 32 weeks, is there any way to not show week numbers over the 2 week shutdown?

                                              ie. up to week 5, then nothing for 2 weeks, then in January start from week 6?

                                              Thanks in advance!

                                              Alex

                                              Replies

                                              Alex Hough
                                              User offline. Last seen 27 weeks 6 days ago. Offline
                                              Joined: 10 Apr 2017
                                              Posts: 7
                                              Groups: None

                                              Brilliant, that worked thanks Ben!

                                              Ben Taunt
                                              User offline. Last seen 6 days 11 hours ago. Offline
                                              Joined: 16 Jan 2012
                                              Posts: 102
                                              Groups: None

                                              Hi Alex,

                                              In the Date Zone Properties (right-click within the Date Zone > Properties), the line currently representing your week numbering will likely state Type = "Elapsed Units", Time Unit = "Weeks".  If you change Elapsed Units to instead be "Working Units", it will reflect your folding calendar's exceptions.  You should then see the change you want in your date zone.

                                              7064
                                              date_zone.jpg

                                              Best wishes,

                                               

                                              Ben @ Powerproject

                                               

                                               