                                              Printing - Page Breaks

                                              1 reply [Last post]
                                              Dominic Planner
                                              User offline. Last seen 31 weeks 21 hours ago. Offline
                                              Joined: 7 Jun 2017
                                              Posts: 21
                                              Groups: None

                                              How do I ensure that the page breaks I have inserted into my programme override the pages I have scaled to, when printing?

                                              At present, the number of pages scaled to seems to be taking precendence and it's not taking into consideration when I have applied page breaks to split my programme. 

                                               

                                              Thanks 

                                              Replies

                                              Mike Testro
                                              User offline. Last seen 2 weeks 4 days ago. Offline
                                              Joined: 14 Dec 2005
                                              Posts: 4403

                                              Hi Dominic

                                              Go to

                                              Print > Options > Scaling > Fit Lines per Page (bottom right corner) > Insert nr of Lines

                                              best regards Mike Testro