                                              Float Path Analysis

                                              4 replies [Last post]
                                              Chris Wilson
                                              User offline. Last seen 21 weeks 6 days ago. Offline
                                              Joined: 21 Oct 2016
                                              Posts: 17
                                              Groups: None

                                              Hi,

                                              I am looking to view the first 5-10 critical paths to help manage a project where more and more activities are losing their float, but cant find a way of doing this easily in Asta.

                                              Obviously the critical path is quite easy to see but the next logical path  behind it thatsay may have 1-2 days float in it is hard to find.

                                              I have looked at using the logic path filter and numbering however these are not great as for instance if a milestone is constrained early then this is shown as a critical path which means the actual critical path  is not shown as logic path 1. It also seems to split at differing stages.

                                              Any help would be appreciated.
                                               

                                              Chris

                                              Replies

                                              Chris Wilson
                                              User offline. Last seen 21 weeks 6 days ago. Offline
                                              Joined: 21 Oct 2016
                                              Posts: 17
                                              Groups: None

                                              Thanks Mike, but its a lenghty programme with  a large number of different float paths. I was hoping to be able to provide full float paths from start to finish so that they could be prioritised. If I filter by total float and copy into a spreadsheet I risk losing the logic and if two float paths have the same total float it wont differentiate between them 

                                              Rafael Davila
                                              User offline. Last seen 3 hours 8 min ago. Offline
                                              Joined: 1 Mar 2004
                                              Posts: 4878

                                              That many scheduling “experts” insist on longest path when it breaks for resource leveled schedules is beyond comprehension.  I do not understand why an activity that belongs to the longest path is more critical than another activity that do not belong to the longest path but have smaller total float. The float path values do not represent a ranked order of criticality.

                                              ORACLE what are Critical Path Activities?

                                              • The longest path is broken when activities are no longer driven by relationships; that is, when activity dates are driven by constraints or resource leveling. Longest path calculation includes interproject relationships. Therefore, activities designated as on the longest path may change depending on whether you schedule a project alone or with its related projects. If a project has interproject relationships and you schedule it alone, the interproject relationships are treated as scheduling constraints.

                                              With resource, financial, supply, space constraints the existing Longest Path theory does not work.

                                              Total floats are useful and sufficient for understanding what activities require maximal attention.

                                              Mike Testro
                                              User offline. Last seen 2 weeks 4 days ago. Offline
                                              Joined: 14 Dec 2005
                                              Posts: 4403

                                              Hi Chris

                                              You can filter on Near Critcal tasks by deducting days from the total float.

                                              Just deduct days from the total float and copy paste the results to a spreadheet

                                              Best regards

                                              Mike Testro

                                              Ben Taunt
                                              User offline. Last seen 6 days 11 hours ago. Offline
                                              Joined: 16 Jan 2012
                                              Posts: 102
                                              Groups: None

                                              Hi Chris,

                                              Is there anything in the Help Files that assists?

                                              http://help.elecosoft.com/powerproject/english/15.0.01/Content/Search.ht...

                                              If not, this sounds like a question for our support team so that they can discuss with you exactly what you're looking to acheive.

                                              Cheers,

                                              Ben @ Powerproject