                                              User defined columns

                                              1 reply [Last post]
                                              Chris Wilson
                                              User offline. Last seen 21 weeks 6 days ago. Offline
                                              Joined: 21 Oct 2016
                                              Posts: 17
                                              Groups: None

                                              Hi,

                                              Does anyone know if its possible to create user defined columns that you can populate from drop down lists?

                                              looking to create  a columns where I can have units such as kg, tonne, m , m2 etc

                                              Regards

                                              Chris

                                              Replies

                                              Ben Taunt
                                              User offline. Last seen 6 days 11 hours ago. Offline
                                              Joined: 16 Jan 2012
                                              Posts: 102
                                              Groups: None

                                              Hi Chris,

                                              You could do this simply using Code Libraries.  Create a Code Library for your units, and then set that as a single select option.  Add the Code Library as a column and a drop down with your options will appear...

                                              Also means you can then easily filter and sort etc.

                                              Ben @ Powerproject 