                                              Import file

                                              3 replies [Last post]
                                              Andy Hudson
                                              User offline. Last seen 2 years 44 weeks ago. Offline
                                              Joined: 18 Oct 2016
                                              Posts: 33
                                              Groups: None

                                              Hi Mike,

                                              I am trying to save file as XER to import it to P6 but got the attached error/warnings.

                                              http://imgur.com/a/E27kh

                                              Please advise me the steps to follow so I can save file as Full as it is without the above warnings and import the whole programme into P6 with same headings and subheadings as in Asta without any error.

                                              Cheers

                                              Replies

                                              Sterling Gallagher
                                              User offline. Last seen 6 weeks 6 days ago. Offline
                                              Joined: 4 Oct 2019
                                              Posts: 12
                                              Groups: None

                                              Hi Mike

                                              Slight variation to this question, I receive files from Asta Power Project saved as an XER file which will import to the Standalone Desktop P6 (SQL lite), but fail when importing to the SQL Network databases.

                                               

                                              Is there a specific method for Asta users to creat an XER file and have you encountered the issue before?

                                              Andy Hudson
                                              User offline. Last seen 2 years 44 weeks ago. Offline
                                              Joined: 18 Oct 2016
                                              Posts: 33
                                              Groups: None
                                              Thanks mike.
                                              Mike Testro
                                              User offline. Last seen 2 weeks 4 days ago. Offline
                                              Joined: 14 Dec 2005
                                              Posts: 4403

                                              Hi Andy

                                              Use File>Safe As>primavera .xer

                                              Job done.

                                              Best regards

                                              Mike Testro